Crane safety operating procedures: 1, the operator must hold a work permit, the operation must be mentally concentrated. 2, when taking over the shift, should be controller, brake, hook, wire rope, safety devices and lubrication status of each lubrication point to check, and a no-load test, check the working condition of the crane's various operating agencies.

Crane safety operating procedures:

1, the operator must hold a work permit, the operation must be mentally concentrated.

2, when taking over the shift, should be controller, brake, hook, wire rope, safety devices and lubrication status of each lubrication point to check, and a no-load test, check the working condition of the crane's various operating agencies.

3, before driving must ring the bell or alarm, operation close to the person should be intermittent ringing or alarm. Boom down, lifting objects below may not be someone.

4, the operator must obey the Division command, according to the Division command signal for operation, is strictly prohibited lifting objects over the head.

5, there are the following cases are not allowed to lift: lifting objects overloaded or weight is not clear; piles of objects tied hanging is not secure; lifting objects on people or floating objects; workplace dim; not allowed to diagonally pull, diagonal lifting of objects; the possibility of explosion of hazardous items; prohibited for pulling piles of similar operations;.

6、Use of limit device or emergency stop switch to stop is not allowed.

7. It is not allowed to adjust and repair machinery and other operations during the working process; the power supply must be cut off and a maintenance signboard or lock must be put on when maintenance is carried out.

8, switch before the main power supply or work in the sudden power failure, should be all the control handle back to zero. Lifting objects are not put down, the operator is not allowed to leave the operating position.

9, when the crane operation is over, the tower crane slewing mechanism should be released, the hook is raised, the trolley stops at the end of the jib (i.e., the most substantial place), and turn off the main power supply; when the wind reaches level 6, the tower crane should be stopped. And turn off the total power supply.

10, the crane is strictly prohibited on the safety device "artificial short or arbitrary adjustment.

11, do a good job in the shift handover records, in the operation of the faults found in a timely manner to reflect to the relevant departments, is strictly prohibited with faulty operation of the crane.